Bulgaria
Bulgaria
Harku-Veskimetsa
Saksa, Isert
Saksa, Landau
Saksa, Ehlscheid
Saksa, Kandel
Saksa, Nunkirchen
Saksa, Deidesheim
2012
-
Water main PE De200mm L=193jm; PE De160mm L=43jm; PE De63mm L=90jm installation by NO-DIG method
-
Assaku, Jüri, Vaida
Gravity pipeline PE De160mm L=187jm installation by NO-DIG method Water main 2xPE De110mm L=314jm ; PE De160mm L=135jm installation by NO-DIG method Pressure pipeline PE De160mm+160mm+110mm L=51jm; PE De160mm L=52jm ; PE De160mm+110mm L=213jm ; PE De160mm+110mm L=72jm ; PE De160mm+200mm L=21jm ; PE De90mm L=69jm ; PE De110mm L=861jm ; 2xPE De110mm L=175jm ; PE De200mm L=87jm ; PE De250mm L=195mm installation by NO-DIG method. Steel pipe Dn219mm L=78jm ja Dn406mm L=75 installation by NO-DIG method
-
Assaku, Jüri, Vaida
Water main PE De50mm L=54jm; Pe De110mm L=125jm installation by NO-DIG method Gravity pipeline PE De160mm L=116jm; case Dn219mm L=122jm; case Dn406mm L=106jm installation by NO-DIG method
-
ELA 054 (Ääsmäe-Muraste- Suurupi)
Communication cable pipeline PE De75mm L=2554m; PE De110mm L=77jm installation by NO-DIG method
-
ELA 060, Harmi
Communication cable pipeline PE De75mm L=153jm installation by NO-DIG method
-
Elva city
Pressure pipeline 2xPE De110mm L=126jm ; PE De110mm L=425jm ; PE De160mm L=155jm ; PE De160mm+PE De110mm L=137jm ; PE De110mm+PE De63mm L=115jm ; PE De110mm+2xPE De63mm L=40; PE De110+PE De90mm ; PE De40mm+PE De63mm L=131jm installation by NO-DIG method. Steel case PE De315mm L=60jm and PE De225mm L=175jm installation by NO-DIG method
-
Elva city
Pressure pipeline PE De50mm L=42jm ; PE De110+63mm L=23jm ; PE De110mm L=297jm ; PE De63+32mm L=33jm ; PE De63mm L=43jm ; PE De63+90mm L=180jm installation by NO-DIG method Gravity pipeline PE De160mm L=58jm installation by NO-DIG method
-
Estlink 2 underground cable (Aseri-Püssi)
Electrical cable case installation PE De400mm L=97jm to the see and L=247jm in the see by NO-DIG method Electrical cable pipeline installation by NO-DIG method : Varja oja PE De315mm L=72m and PE De250mm L=72m Varja oja (extra works) PE De315mm L=68m and PE De250mm L=68m Kiviõli, Varja rd. PE De315mm L=60m and PE De250m L=60m Kraav PE De315mm L=50m and PE De250m L=50m Lüganuse Cemetery road PE De315mm L=50m and PE De250m L=50m Purtse river PE De315mm L=324m and PE De250m L=324m Purtse - Lüganuse rd. PE De315mm L=50m and PE De250m L=50m Main gas PE De315mm L=59m and PE De250m L=59m Sõreda creek PE De315mm L=56m and PE De250m L=56m TLN-Narva rd. 132,98km PE De315mm L=50m and PE De250m L=50m
-
Forelli str., Tallinn
An existing pipeline Dn200mm replacing to new pipeline PE De200mm L=714jm and Dn250mm replacing to PE De250mm L=372jm, by NO-DIG method
-
Haljala
Water main PE De110mm L=143jm by NO-DIG method
-
Hiiumaa
Communication cable pipeline PE De75mm L=351jm installation by NO-DIG method
-
Hüüru
Water main PE De90mm L=303jm; steel case Dn377mm L=20jm; Dn426mm L=14jm ; Dn219mm L=23jm installation by NO-DIG method. Pressure pipeline PE De90mm+PE De110mm in case 2xDe160mm L=94jm installation by NO-DIG method. Steel case Dn219mm L=55jm, Dn406mm L=37jm installation by NO-DIG method.
-
Järve rd., Tallinn
An existing water main Dn110mm replacing to PE De110mm L=66jm; Dn300mm replacing to PE De300mm L=80jm by NO-DIG method
-
Jõelähtme
Cable pipeline 3xPE DN110mm L=3x25=75jm installation by NO-DIG method
-
Jõhvi, Raudtee str.
Case PE De250mm installation for water main PE De160mm L=74jm by NO-DIG method
-
Jõhvi, Tartu rd. - Kaare str.
Case PE De200mm installation by NO-DIG method for water main PE De110mm L=41jm Water main PE De63mm L=60jm; PE De32mm L=12jm; PE De110mm L=23 installation by NO-DIG method
-
Kadaka str. 76d
Communication cable PE De110mm L=37jm; pipe PE De110mm L=13jm installation by NO-DIG method
-
Kadrioru park
Pressure pipeline PE DN250mm L=298jm installation by NO-DIG method
-
Kehra
Pressure pipeline PE De160mm L=411jm ; PE De110mm L=180jm and PE De63mm L=52jm installation by NO-DIG method
-
Kehra
Water main PE De200mm L=91jm installation by NO-DIG method Pressure pipeline PE De110mm L=63jm ; 2xPE De110mm L=365jm installation by NO-DIG method
-
Kehra
Pressure pipeline 2xPE De110mm L=302jm and case 2xDn200mm L=160jm installation by NO-DIG method
-
Kehra
Water main PE De110mm L=108jm installation by NO-DIG method
-
Kehra city
Water main PE De110mm L=376jm installation by NO-DIG method
-
Kehra city, Laste and Aia str.
Water main PE De110mm L=90jm and pressure pipe line PE De110mm L=89jm installation by NO-DIG method
-
Kehra city, Ülejõe village
Pressure pipeline 2xPE De110mm L=2x100=200jm installation by NO-DIG method
-
Kehra-Lilli ja Raasiku-Võidu overhead lines replacement
Electrical cable pipeline PE De160mm L=129jm installation by NO-DIG method
-
Kohila
Pressure pipeline PE De63mm L=75jm ; PE De110mm L=715jm ; PE De160mm L=71jm installation by NO-DIG method Water main PE De63mm L=158jm, PE De110mm L=477jm, PE De 32mm L=66jm, PE De90+PE De63mm L=120jm, PE De160mm L=98jm installation by NO-DIG method Gravity pipeline PE De200jm L=25jm ; PE De160mm L=31jm installation by NO-DIG method
-
Laagri
Water main PE DN160+PE De110mm L=145jm; PE DN160+PE De200m L=72jm installation by NO-DIG method
-
Laagri, Hoiu str.
Pressure pipeline PE DN160+PE De110mm installation by NO-DIG method
-
Laagri, Hoiu str.
Pressure pipeline PE De110mm L=211jm installation by NO-DIG method
-
Laagri-Nõlvaku-Sillaku str.
Water main PE De110mm L=188jm ; PE De75+63mm L=51jm installation by NO-DIG method
-
Laitse village
Pressure pipeline PE De110mm L=201jm installation by NO-DIG method Gravity pipeline PE De160mm L=135jm renovation by "pipe burst" method
-
Lammasmäe, Virgu, Nigula parish, under the Kunda river
Electrical cable pipeline PE DN110mm L=164jm installation by NO-DIG method
-
Luige
Gravity pipeline PE De160mm L=56jm ; PE De200mm L=30jm Pressure pipeline PE De56jm L=56jm ; PE De200mm L=30jm ; 2x PE De110mm L=60jm installation by NO-DIG method
-
Märjamaa - Koluvere tee
Communication pipe line PE Dn63mm and De75mm installation by NO-DIG method
-
Märjamaa FOK
Communication cable PE DN63mm L=112jm ; PE De75mm L=381jm ; PE DN110mm L=189jm installation by NO-DIG method
-
Märjamaa-Tenuse-Koluvere
Cable pipeline PE De63mm L=223jm, PE De75mm L=83jm installation by NO-DIG method
-
Merivälja development II, Ranniku str. Aia str.
Pro Fuse PE De90x8,2+25mm a wired protection tube L=929jm; PE De63x8,2mm L=62jm installation by NO-DIG method
-
Merivälja development ll, Ranna str.
PE De90x8,2 (Pro Fuse) pipe L=368jm installation by NO-DIG method
-
Metsa str.
Gas main PE De110mm installation by NO-DIG method
-
Mustamäe hospital C-building Sütiste str.
Cable pipeline 3xPE De160mm L=66jm; 4xPE De160mm L=424jm; PE De160mm L=1154jm installation by NO-DIG method
-
Narva, Kadastiku str.
Pressure pipeline PE De160mm L=90jm installation by NO-DIG method
-
Otepää, Pühajärve holiday Home
Case PE De160mm+PE De110mm L=40jm and steel case Dn219mm+Dn323mm L=40jm installation by NO-DIG method
-
Paldiski
Directional drilling PE De110mm L=917jm ja PE De160mm L=486jm
-
Paldiski
Water main case PE De280mm L=17jm and PE De160mm L=17jm installation by NO-DIG method Water main PE De225mm L=851jm by NO-DIG method Water main PE De110mm L=513jm ; PE De225mm L=662jm installation by NO-DIG method. Water main PE De200mm L=330jm; PE De110mm L=221jm renovation by NO-DIG method.
-
Paldiski
Water main PE De110mm L=211jm; PE De63mm L=64jm; PE De50mm L=65jm installation by NO-DIG method
-
Paldiski rd. 52
Water main PE De110mm L=11jm installation by NO-DIG method
-
Paldiski rd.80
Water main 2xPE De75mm L=116jm; gravity pipeline PE De350mm L=29jm installation by NO-DIG method
-
Panga village
Steel case Dn400mm L=21jm installation for gravity pipeline by NO-DIG method
-
Pargi str., Viimsi
Sewerage pipeline PE De200mm L=169jm renovation by NO-DIG method
-
Peterburi tee 2, Tallinn
Case DN400mm L=240jm installation by NO-DIG method
-
Püssi
Water main PE De63mm L=1915jm ; PE De50mm L=759jm ; PE De32mm L=52jm ; PE De110mm L=756jm installation by NO-DIG method
-
Rakke
Gravity pipeline PE De200mm L=84jm; watermain PE De110mm L=463jm, PE De63mm L=104 - installation by NO-DIG method
-
Rakke, Vetiku
Water main PE De110mm, De50mm, De63mm, De75mm L=823jm installation by NO-DIG method
-
Rakke, Viru-Jaagupi
Water main PE De110mm L=564jm; PE De32mm L=160jm; PE De50mm L=153jm; PE De75mm L=18jm; PE De63mm L=183jm installation by NO-DIG method
-
Rakvere
Water main PE De160mm L=58jm installation by NO-DIG method
-
Rakvere
Water main PE De160mm L=564jm installation by NO-DIG method
-
Rakvere, Lepna str. Jõepere str.
Gravity pipeline case De406mm, De219mm L=58jm; water main case PE Dn160mm L=32jm; PE Dn63mm L=23jm - installation by NO-DIG method
-
Rannamõisa str. 16a and 18 house connection
Pressure pipeline PE De110mm L=100jm installation by NO-DIG method
-
Riisipere-Kernu str. Metsa str.
Case De200mm for gravity pipeline De160mm L=53jm; case De32mm for pressure pipeline De50mm L=16jm; case De140mm for pressure pipeline De110mm installation by NO-DIG method
-
Roela-Rakke
Pressure pipeline PE De160mm L=1114jm; PE De110mm L=645jm installation by NO-DIG method Case De160mm L=162jm installation by NO-DIG method
-
Saaremaa
Communication cable pipeline PE De75mm L=1240jm ; PE DN110mm L=581jm and pipe PE De110mm L=727jm installation by NO-DIG method Water main PE De225mm L=256jm by NO-DIG method
-
Saku
Water main PE De110mm L=341jm installation by NO-DIG method
-
Saku
Pressure pipeline PE De110mm L=42jm installation by NO-DIG method
-
Saku borough, Männi str. and Western substation
Cable pipeline PE De160mm L=106jm installation by NO-DIG method
-
Saue
Water main PE De200mm L=279m; PE De63mm L=47jm; PE De110mm L=36jm installation by NO-DIG method
-
Saue, Vanamõisa village
Pressure pipeline PE De110mm L=4x12+2x12=72jm installation by NO-DIG method
-
Savala
Gravity pipeline installation PE De200mm L=45jm, renovation PE De160mm L=96jm Water main installation PE De110mm L=19jm; PE De40mm L=83jm; PE De32mm L=58jm - by NO-DIG method
-
Sihi-Haava str.
Gas main PE De125x11,4mm (Pro Fuse) L=159jm by NO-DIG method
-
Sillamäe city
Cable pipeline PE De110mm L=42jm installation by NO-DIG method
-
Smuuli str.
Pressure pipeline PE De225mm L=29jm installation by NO-DIG method
-
Smuuli str.
Electrical cable pipeline PE De160mm L=6x19+6x17+4x43=388jm installation by NO-DIG method
-
Tammiku
Pressure pipeline PE De110mm L=411jm installation by NO-DIG method. Steel case Dn400+Dn219mm L=49jm installation for gravity pipeline Dn200 by NO-DIG method
-
Türisalu
Pressure pipeline PE De110,160mm L=200jm installation by NO-DIG method
-
Vääna
Pressure pipeline PE De110mm L=211jm; PE De110mm in case Dn160mm L=88jm installation Gravity pipeline PE De160mm L=25jm installation by NO-DIG method
-
Vaida
Case PE De160mm L=55jm installation by NO-DIG method
-
Väike-Paala
Sewerage pipeline PE DN225mm L=160jm installation by NO-DIG method
-
Vana-Narva mnt. Vopak electric cable
Electrical cable pipeline PE De160mm L=484jm installation by NO-DIG method
-
Varbla
Cable pipeline PE De75mm L=183jm installation by NO-DIG method
-
Vene theater, Tallinn
Sewerage pipeline PE DN200mm L=38jm installation by NO-DIG method
-
Viadukti str., Tallinn
Existing sewerage Dn300mm replacement for a new one PE De315mm L=107jm by NO-DIG method
-
Viljandi
Water main PE De110mm L=136jm installation by NO-DIG method
-
Viru-Jaagupi borough
Water main PE De32,63,50,110mm L=753jm installation by NO-DIG method
-
Volta-Electric power station Ranna 100kV cables installation
Cable pipeline 2x3xPE De225mm L=292jm installation by HDD method