Pärnu mnt. 7-Suur-Karja tn., Tallinn - Steel pipe DN800 installation NO-DIG method
Valjala borough, Saaremaa - Water and pressure pipe PE De63, 75,110,160 installation L=744jm NO-DIG method
Under the Tallinn - Moskow railway KSRV (Kotka str.) - Case DN1200 mm installation L=150jm by NO-DIG method
Ülemiste, Tallinn - water and pressure pipeline PE De63mm instalation L=148jm and PE De90mm instalation by NO-DIG method L=148jm
Ülemiste road junction - replacement of air power lines 110kV to the underground electrical cable 3xPE DN200mm L=484jm
Kristiine, Tallinn, under the railway
Muuga port, under the petrol pipeline - cable pipeline PE De160mm instalation by NO-DIG method L=144jm
Introduction
OÜ Agio Ehitus was founded in 1991.
Since then the company laid more than a dozen kilometers of pipelines for various purposes. Over the last ten years one of the main activities of Agio Ehitus is laying the pipelines with the "closed method", this is achieved by using different types of equipment and techniques. We have extensive experience in laying pipelines in rocky soils, quicksand, clay, sand, and etc.By using the closed cut methods of construction of utility lines, we can often perform works quicker and cheaper than when using the open cut method. The costs for removal and disposal of soil as well as labour costs are reduced, furthermore there is no need to reroute traffic. It is also possible to reduce the risk of damaging the existing underground utilities, compared to open cut excavation methods.

Additionally, in many soils in which utility lines are built and where exclusive standards are valid and environment protection level is high, there is no alternative to a closed cut method.
OÜ Agio Ehitus uses equipment from world-leading manufacturers in the field of horizontal directional drilling and microtunnelling. These brands include Vermeer, Ditch Witch, Mc Laughlin, Wamet, No-Dig Scandinavi.
Company and employees
Agio Ehitus holds licenses for operating in the following fields of activities:
- construction of outside networks of water supply and sewerage;
- construction of outside heating systems;
- construction supervision;
- general construction works;
- repair works.